    Construction Diary

Boat Landings

To maintain the wind turbines, personnel access them by boat, and therefore each pile has been fitted with a “boat landing” comprising a ladder and two fenders. The fenders are positioned one either side of the ladder and project out from the pile, allowing a small vessel carrying maintenance crew to temporarily secure itself alongside the ladder to transfer personnel. The boat landings were transported out to site and installed using the vessel “Forth Guardsman”.







back top





Forth Guardsman installing a boat landing