The turnkey contract to construct the wind farm was awarded to REpower UK - a joint venture between wind turbine company REpower Systems AG and specialist engineering company Peter Brotherhood Ltd.

In addition to the installation and commissioning of the wind turbines, REpower UK was also responsible for providing the necessary civil and electrical infrastructure, as well as a five-year warranty, operation and maintenance package.

To deliver the contract, REpower UK subcontracted McNicholas Construction Services Ltd to undertake the civil and electrical works on site.

npower renewables was responsible for providing a grid connection and access to the site, in conjunction with Western Power Distribution and Forestry Commission Wales respectively.

Wind turbines

The wind turbines installed at Ffynnon Oer are REpower MM70 2 megawatt turbines, which comprise a 58 metre (m) tower with a 70 m rotor diameter.

Construction diary

The approximate timeline for the different components of construction was as follows:

  • Access track from public highway to site entrance
    May 2005 - June 2005


  • On-site access tracks
    June 2005 - November 2005


  • Substation
    September 2005 - March 2006


  • Wind turbine foundations
    October 2005 - April 2006


  • Wind turbines
    November 2005 - April 2006


  • Underground cabling
    December 2005 - April 2006


  • Grid connection energised
    March 2006


  • First power generation
    May 2006


  • Commissioning of wind turbines
    May 2006 - June 2006

The substation begins to take shape


Contractors prepare to fill one of the turbine foundations


Preparing a wind turbine's "in-tower" electrical components


Attaching the blades to the first wind turbine to be installed on site